– Location: Baghdad/ Al.Taji Base
– Client : Iraqi Ministry of Internal Affairs
– Start & Finish Date: Jan./2007 – Feb./2007
– Contract amount : 1.820.000 US Dollar.

Project Summary:
Constructing of sub road at Al.Taji base. The work included sub grade excavating & backfilling with the required compaction then spreading of class B sub base with the leveling and compacting. The total length of road is (2.3 km).