– Location: Baghdad
– Client: Baghdad Governorate.
– Start & Finish Date: Jul/2007 – Sep/2007
– Contract amount: 1.500.000.000 ID.

Project Summary:
Demolishing damaged parts of damaged span due to terrorist action, remove debris off site, rebuilding the span with pre-cast pre stressed concrete girders (18.5 m span) with their pads, then casting the reinforced concrete deck of the span, shoulders paving, supply and install missed parts of guardrail with painting.