– Location: Baghdad (Abo.Ghraib, Boaitha & Al.dorah)
– Client : USACE
– Start & Finish Date: Oct. /2009 to May /2010
– Contract amount: 16.000.000 USD

Project Summary:
Constructing guard towers, administrative building 120 m2 area & rehabilitant of existing buildings. The work included supplying & installing concrete barriers and construction of CMU blocks, providing all electrical wiring and installing of (100KVA) generator with all electrical wiring.